Use the following checklist to plan and track the Lotem 400 installation.
| Installation item | Completed |
| 1 | Site preparation |
| 2 | Floor space |
| 3 | Electrical requirements |
| 4 | Environmental conditions |
| 5 | Air supply |
| 6 | Network / modem requirements |
| 7 | Hardware installation |
| 8 | Check for damage |
| 9 | Unpack and position platesetter |
| 10 | Voltage setting |
| 11 | Remove shipping guards |
| 12 | Height adjustment of platesetter |
| 13 | Plate conveyor assembly and connection |
| 14 | Processor positioning |
| 15 | Power and air compressor connection |
| 16 | Operation monitor connection and cable setup |
| 17 | Power up |
| 18 | Network setup / time setting |
| 19 | Software check and start up |
| 20 | Brisque unpacking and setup |
| 21 | Brisque connection (TCP/IP address, fibers) |
| 22 | Brisque configuration |
| 23 | Customer configuration setting |
| 24 | Set press formats |
| 25 | Set plate size |
| 26 | Lotem check |
| 27 | Drum motion |
| 28 | Interlocks system |
| 29 | Laser status |
| 30 | Full load / unload cycle |
| 31 | Exposure tests |
| 32 | Calibration tests - only if necessary |
| 33 | Processor check |
| 34 | Check file position on height axis (edge detection) |
| 35 | Excurve calibration |
| 36 | ATP of customer formats |
| 37 | Perform a customer job |
| 38 | Calibration |
| 39 | Press runs |
| 40 | Tone reproduction buildup |
| 41 | Training |
| 42 | Hardware training |
| 43 | Brisque functionality training |
| 44 | Workflow setup |