Dolev 800/800V/800VČ TIC -  Installation
Punch/On-Line Conveyor

Installation

Introduction

See FCO17436 -   05/05/93 Light Area Harness
See FCO 17851 -   15/06/93 Manifold installation
See FSB 378 -   19/01/94 Changes on Punch units
See FCO 18908 -   09/03/94 Punch Basket Big R
See -   09/12/96 Dolev 800 Calibration with the Brisque
See -   26/01/97 Dolev 800 Punch Calibration with the Brisque

Procedures for installation of the punch system are comprised of the following activities. The approximate duration of each activity is also given:

Activity Duration
  1. Host software and hardware compatibility verification, and hardware upgrade.
1/2 hour
  1. Compressed air supply system installation
1 to 2 hours
  1. Machine covers removal.
1 hour
  1. Punch assemblies installation.
6 hours
  1. Punch assemblies final adjustment.
3 to 4 hours
  1. Compressed air tube and slug system installation, electrical wire final routing, and final speed adjustments.
2 to 3 hours
  1. Repeatability and registration test plots.
1 to 2 hours
  1. Image offsets setup in accordance with customer-approved layout.
1 hour
  1. Machine covers re-installation.
1 to 2 hours
  1. Repeatability and registration final test plot.
1/2 hour