Planned maintenance is performed every six months.
Before going to the site:
Plot the grid and ATP test in the resolution that the customer usually works with. Look for any patterns or effects, overall screen quality, and registration. Keep those plots as a reference.
Important: While performing maintenance, do not take apart or dismantle any part not specified for checking, cleaning or greasing.
Objectives: Check safety first! Determine
that all Dolev 4Press components are safe to operate and to work on. Walk around
the entire device to examine the exterior and surroundings for damage and any
issues that may require further investigation or repair.
Time needed: 20 minutes (Device can be
returned to customer any time.)
| Safety and Exterior Evaluation | What to Do | What to Look For | Procedure
Parts |
|---|---|---|---|
| Site conditions | Check that the site conditions are within the specifications, and inform operator of any unfit conditions. |
|
|
| Door and side interlocks | Open each door. | Ensure that the safety interlocks are operating correctly. | Panel operation Detectors status |
| Panels, doors and covers | Visually inspect the overall condition of all surfaces, hinges. | Smooth opening and closing, good condition | Ordering information |
| Operating panel and keys | Visually inspect and activate all four keys and buttons |
Objectives: Determine that the Dolev 4Press is operating
correctly. Watch and listen. Note irregularities for further investigation.
Time needed: 20 minutes (Device can be
returned to customer any time.)
| System Operation | What to Do | What to Look For | Procedure
Parts |
|---|---|---|---|
| Operator feedback | Speak with the operators and prepress manager. |
|
|
| Operator training | Make sure the operators understand how to operate the device safely. | Use customer training check list. | |
| Firmware | Check firmware version | The latest machine firmware is installed | Release notes and firmware downloads |
| Settings | Backup settings |
Save all tables on a rescue diskette |
501V50331A - S/W rescue diskette |
| **Load film into the drum.** | |||
| Rocker assy | Watch and listen. | When loading drawer is closed, rocker assy closes without touching optomech side flanges. | |
| Loading rollers and guides | Watch and listen. | Smooth, symmetrical and quiet movement of film. | |
| Drum air release grooves | Watch, and use a flashlight to see. | Film should be smoothly spread in the drum with no visible air bubbles. | |
| Cutter | Watch and listen. | Smooth quite operation and even cut edge of film. | |
| Unload rollers and guides | Watch and listen. | Smooth quite operation. | |
| **Move carriage from HP to EP** | |||
| Carriage | Listen. | Listen for any irregular noises. | |
| Dynamic optic chain assembly | Watch and listen. | Dynamic optic chain opens and rewinds smoothly. | |
Note: To properly assess image quality, the processor should have been serviced and filled with fresh chemistry within the last 24 to 48 hours.
| What to Do | What to Look For | Procedure
Parts |
|
|---|---|---|---|
| **Expose a large gray scale in three of the client's favorite formats.** | |||
| Static Optic | |||
| Laser | From the service utility, run ND filter graph. | Value should be >40,000. "Normal" value is 60,000. | Replace the static optic unit if value is <40,000. |
Objectives: Check everything, then go back and
repair or adjust as required.
Time needed: 3-4 hours
| What to Do | What to Look For | Procedure
Parts |
|
|---|---|---|---|
| ECOs/FCOs | Check that all mandatory FCOs are implemented on the Dolev 4press. | FCO list | |
| E-box and P-box board revision levels |
|
|
|
| Data box (if exists) |
|
Check VLSI comp level. | VLSI comp level |
| Machine parameters |
|
|
Rescue diskette |
| Detectors | Run diagnostics to check detectors. |
|
|
Loading system |
|||
| Loading cassette |
|
|
|
| Film-in detectors |
Manually activate film-in detectors. |
Detector arm should be free. | |
| Load/unload rollers |
|
|
Adjusting load/unload roller tension |
| Cutter |
|
|
|
| Film transport guides | Clean the guides with a clean cloth dampened with alcohol. |
|
|
| Unloading cassette |
|
Check for light leakage. Totally clear film indicates no light leakage. | |
| Drum cavity and guide beam |
|
||
| Drum air release grooves | Clean with medical needle (22G1.5 or similar). | ||
| Film attachment to drum |
|
There should be no air bubbles between the film and drum. |
Adjusting load/unload roller tension |
| Film feed counters |
Run diagnostics, and check. |
|
Replace if required. |
Carriage - dynamic optic assembly |
|||
Leadscrew |
|
Thread should not be bent, screw should be in good condition. | Use ball nut greaser (507B26966) |
|
|
Check pressure on blue coupling and adjust if required. | Measurement of coupling compression is <1.5 mm | Adjust coupling pressure |
| Dynamic optics |
|
Important: If spinner is under warranty, do not clean it! The warranty expire date is located on a label on the spinner. |
Installing/uninstalling dynamic
optics
|
| Penta prism / cube | Clean. | ||
| Fiber connectors |
|
||
Punch assembly |
|||
| Punch (if installed) | Remove slugs and clean container. | ||
| Punch assy |
|
||
Power supply |
|||
| Power unit voltage | Run dignostics to check voltage levels, and replace power box, if required. | ||
| **Expose a large gray scale in three of the client's favorite formats. Check for patterns and uniformity, and compare to reference.** | |||
To complete the PM, the check list must be signed off by the customer and returned to Creo.