Installing an Autoloader Ready (AL-Ready) Trendsetter VLF

It takes one day to install an AL-Ready Trendsetter VLF shipped new from the factory.
[To upgrade and AL-Ready Trendsetter VLF with the Autoloader option, see the Upgrading an AL-Ready Machine page]
[To perform a retrofit, see the Field upgrade page]
[To install a complete Trendsetter VLF AL, see the Factory Install page]

Notes:

Installation | Printed Documents | Tools

Installation Procedures

  1. Check the site preparation
  2. Unpack & position
  3. Install the base Trendsetter VLF
  4. Install the imaging head. See the Thermal Head installation page.
  5. Install skins and guard rail
  6. Clean up
  7. Install the Workstation
  8. Test the system (not yet available)
  9. Align the head. See the Head Installation procedure(doc #77-0074A)
  10. Configure the system.
  11. Complete the Installation Test Procedure (ITP): for Print Console
  12. Train the operator. See the Operator checklist.

Procedure Checklist (Excel file):  a summary of the procedures for installing an AL-Ready Trendsetter VLF.
Note: This checklist must only be used as a reference sheet for those who are fully trained and experienced with installation of the VLF TS AL system.

Tools

Tools: Description of installation tools and jigs, with photos